2019 Bond Projects

The Brock ISD Board of Trustees approved the Citizens Advisory Committee’s (CAC) recommendation of a $21,360,000 bond proposal, which was presented on the November 5 ballot as a single proposition and does not include a tax rate increase.

The CAC was led by community chair Mike Kirk and included 21 fellow community members. The $21,360,000 bond proposal will address classroom capacity at the secondary level, additional school buses, along with safety and technology upgrades district-wide. 

The bond package includes funding for distrct wide updates and renovations to two existing campuses. 

 

DISTRICT-WIDE UPDATES

  • Enhanced security features at all campuses

  • Five new buses to replace a portion of our aging fleet

  • Technology upgrades to increase infrastructure and access points

Schedule: Completed fall 2020 (Buses purchased over next five years)

Budget: $700,000*

 

JUNIOR HIGH SCHOOL

• Classroom addition increasing capacity to 650, including an additional gym

• Increased capacity will accommodate future growth along with moving sixth grade from the intermediate school


Schedule: Construction begins fall 2020, open fall 2021
Budget: $9,500,000*

 

HIGH SCHOOL

• Classroom addition increasing capacity to 800, including additional career and technology program spaces

• Lab addition at the agriculture building for welding and fabrication


Schedule: Construction begins spring 2021, open fall 2022

Budget: $10,160,000*

 